12
57
Our Hours Today:
Closed

Project Updates

The Capital Facilities Planning construction project update page is intended to let you know what projects are under construction around campus and how they may impact our students, faculty, staff, and visitors.

The page is typically updated every two weeks and will follow the current college semester. Projects are listed alphabetically and given a short synopsis of what construction work is scheduled and what the campus can expect as far as disruptions and/or inconveniences. There are also links to each of the projects site pages for those looking for additional information.


Week of September 14 through Week of September 21

We hope everyone is safe, well, enjoyed the summer, and are settling back into to the new school year. Here’s what we have been working on and will be working on over the next few months.

Administration Building Exterior Renovations

Construction will continue over the Summer and will into the Fall semester.  The contractor will be completing their roofing work and replacing the exterior windows.

Heating Plant Boiler Upgrades

Contractor has been working all summer, and the 1st new boiler has been delivered.  The two new additional boilers have also arrived.  They will be completing their work this Fall.

Interior Upgrades at Olde Apartment Complex

Construction continued this summer, with minor punch list work remaining.

Rehab of Bookstore

The contractor continued their work over the summer.  We’ve had a few delays but will be completed the work this Fall.

Site Improvements for Accessibility - Phase 3

Construction work is complete in the East 1A parking lot.  Work is currently progressing at the Commons apartment complex. Central 2 and East 2 and 3 parking lots.